What it governs
Lets a registered architect approve building plans, and now issue the occupation certificate, for houses on individual plots in licensed residential and industrial plotted colonies. The DTP office gets a short window to object.
What it means for an owner or buyer
- Under the 2011 policy, the DTP had 5 working days to point out deficiencies. If none came, the plan was treated as accepted and the architect issued the approval.
- The DTP's check is limited to documents and fees, setbacks and gate position, and coverage, FAR and height.
- Since 16 November 2022, the architect issues the OC for a house in a licensed plotted colony within 8 working days. The DTP checks 10% of cases.
- If a self-certified OC is found wrong, it can be withdrawn and floor registration on that plot can be stopped. The owner bears the cost of fixing violations.
Key numbers
| 2011 policy, para 4 | DTP to convey deficiencies within 5 working days, failing which deemed accepted 29 Oct 2011 |
|---|---|
| HBC-2017 code 4.11 (as applied by TCP order of 13.04.2018) | Self-certified OC for residential plots, commercial sites up to 15 m height and 1,000 sqm, and industrial buildings of all sizes; OC within 8 working days 13 Apr 2018 |
| SOP of 16.11.2022 | Architect issues OC within 8 working days; DTP checks 10%, STP 5% 16 Nov 2022 |
Amendment timeline
- 13 Apr 2018 — Office order on grant of occupation certificate under self-certification following amendment of HBC-2017 (22.12.2017).
- 16 Nov 2022 — Standard procedure making the architect the competent authority for self-certified OCs of houses in licensed residential plotted colonies (Memo No. Misc-2484-D/2022/34493-94).
Applies to
Licensed colony