Stilt plus four floors (S+4) — stayed since April 2026, and what the policy said

The High Court stayed Haryana's S+4 order on 2 Apr 2026 (CWP-PIL 212 of 2024); TCP put all S+4 approvals on hold on 3 Apr 2026.

4 min readChecked on 28 Nov 2026

What it is

S+4 is on hold. On 2 April 2026 the Punjab & Haryana High Court, in CWP-PIL No. 212 of 2024 (Sunil Singh vs. State of Haryana and another), restrained the State from going ahead with the Stilt + 4 floor policy for residential plots and stayed the order of 2 July 2024 "for the time being".

The next day, 3 April 2026, the Director, Town & Country Planning (Memo No. Misc-2339-L(S+4)/2026/10996-999) asked HSVP, ULB, HSIIDC and Housing for All to put all S+4 approvals on residential plots on hold until the High Court removes the embargo. TCP also directed:

  • No layout plan, zoning plan or service plan estimate to be approved at a density of 18 persons per plot, or for S+4, in the meantime.
  • Applications for S+4 approval to be disabled on the S+4 portal and on HOBPAS with immediate effect.

TCP's order notes that the Court, at para 10, linked the issue to Gurugram's infrastructure: sewage, drainage, STPs, traffic and flooding.

S+4 means stilt parking on the ground, plus four floors above, on a residential plot.

When you need it

  • Buying a residential plot priced on four floors.
  • Buying a floor in an S+4 building, built or planned.
  • Holding an S+4 approval and deciding whether to build.

Documents

  • The building plan approval letter and its date.
  • The approved layout plan of the sector or colony, showing its density (persons per plot).
  • For a 13.5-persons layout: proof of road width and the consent agreements or setback plan.
  • Occupation certificate, if the building is complete.
  • The latest High Court order and any later TCP order on the S+4 portal.

Steps

  1. Check today's status. Read the latest order in CWP-PIL 212 of 2024 and TCP's orders page before any decision. The hold lasts until the Court lifts it.
  2. Check the date of any approval. Find when the plan was sanctioned. TCP had already kept fresh S+4 approvals in abeyance from 23 February 2023 before the 2024 order. Ask the approving office how the 2026 stay treats an approval you hold.
  3. Read the layout density. Under the 2 July 2024 directions, S+4 was allowed outright where the layout plan was approved at 18 persons per plot, including DDJAY colonies whose service plan was approved or revised at that density.
  4. For 13.5 persons per plot, the 2024 order allowed S+4 only where the plot had access from a 10 m or wider road and either an irrevocable mutual consent agreement with all adjoining owners, or a 1.8 m side setback on all floors. Owners who refused consent became ineligible for S+4 later.
  5. Check the purchasable FAR paid. The 2024 order raised PDR rates for plots above 250 sq m (approx. 299 sq yd). In the hyper potential zone the new rates per sq m were Rs 4,500 (above 250 up to 350 sq m), Rs 6,500 (above 350 up to 500 sq m) and Rs 10,000 (above 500 sq m).
  6. Get the agreement right. If you buy now, write the stay into the agreement: what happens if S+4 is not allowed.

Usual time and cost

No S+4 approval can be obtained while the hold is on. The 2024 order also offered refunds to HSVP auction buyers who chose not to build S+4: unused PDR refunded with 8% interest if applied within 60 days of the order. That window has passed. Other costs depend on the plot and zone, and we can work them out on request.

Common problems

  • Priced on four floors. A plot or floor priced on S+4 may lose value if the stay continues.
  • Floor sold before approval. A buyer of a "fourth floor" with no sanctioned plan holds a promise, not a unit.
  • Separate fourth-floor unit. Registration of a fourth floor as a separate unit was governed by an earlier 2019 policy. Check how the stay affects it before buying.
  • Infrastructure condition. The 2024 order said infrastructure augmentation would be funded from IAC collected on S+4 approvals. The Court's concern was the same infrastructure.
  • Mixing up policies. S+4 on residential plots is separate from group housing or TOD FAR. See TOD zone check.

Governing rule

Checked on 28 Nov 2026 against: Town & Country Planning Dept, Haryana — order of 03.04.2026 on the High Court interim order (with the order of 02.04.2026 attached); Town & Country Planning Dept, Haryana — directions on Stilt + four floors, Memo No. Misc-2339(L)(S+4)/2024/19679-83, 02.07.2024. Something changed? Tell us.